2/08/24 – 3/06/24 CPFM Compound Increased Construction Traffic Advisory

UPDATE:
Due to delays in compacting and Geotech inspections, the end date has been moved to March 6th.

 

Begin:  Thursday, February 8, 2024

End:      February 16,  Wednesday, March 6, 2024

Building(s) or Area(s) Affected:  CPFM Compound

Scope:  Hoffman Construction will be staging backfill rock material west of CPS & the tank. See attached map.

Services Impacted:  There will be Hoffman truck traffic to and from the staging area during daytime and evening hours, for the duration.

Work Performed By:  Hoffman Construction

ContactDenise Stewart, CPFM Owner’s Representative, 541-346-2280 or 541-335-1258

Current construction and impacts information can be found on the UO Maps site.