Begin:  Tuesday, March 21, 2023, at 7:30 am

End:      Tuesday, March 21, 2023, at 10:30 am

Building(s) or Area(s) Affected:  Oregon Hall, 2nd Floor Financial Aid Offices L287, 287A, 267, 268, H277, 272, 274, 278, 279, 282, 284, 286, H285, 281, 280

Scope:  As part of a structural investigation for the sloping third floor, we have engaged a structural engineer. The engineer and facilities assistants will be accessing the third floor structure for a visual assessment. This requires access to the 2nd floor Financial Aid department offices. The team will use a ladder to access the ceiling area. The areas to be investigated are included in the attached map. It should only take a few hours to access and view the different points the engineer is interested in.

Services Impacted:  When we enter certain offices, we will likely interrupt the occupant for a short time. They may need to step out so the ladder can access the ceiling in their office.

Work Performed By:  Hohbach-Lewin and Facilities

ContactJanell Cottam, CPFM Owner’s Representative, 541-346-7536

Current construction and impacts information can be found on the UO Maps site.