UPDATE:
S-2 has completed the repairs and the utility staff is slowly bringing steam up to pressure.
It is expected to be fully pressurized within the next 2 hours.
Begin: Wednesday, September 14th, 2022 – effective immediately
End: Unknown Wednesday, September 14th, 2022
Building(s) or Area(s) Affected: Campus
Scope: The Utilities and Energy is currently investigating a major steam leak found in the tunnel under Franklin Blvd. We believe the leak is coming from the clean steam line (Autoclave) and have shut off the Autoclave so we can investigate. Currently we do not have an estimate of time when steam will be restored.
Services Impacted: Autoclave steam will be offline until the repair can be made.
Work Performed By: S2 Industrial and CPFM Utilities & Energy
Contact: Paul Langley, CPFM Interim Co-Dir Utilities & Energy, 541-346-5387
To view current construction and impacts, visit UO Map.