Begin: June 6, 2022 at 12:00 PM
End: June 8, 2022 at 12:00 PM
Building(s) or Area(s) Impacted: Streisinger, Huestis, Willamette and Lokey Labs
Scope: Due to the installation of a flow meter, valve, and repair corroded piping, the chilled water will be shut down. Process cooling will be on a backup cooling water during the shutdown.
Services Impacted:
• Chilled water will be off at this time
• Work in the utility tunnel accessed from Huestis 006A and Streisinger 083A.
Work Performed By: Utilities & Energy and S2 Industrial
Contact: Kyle Wilson, CPFM Utilities Maintenance Manager, 541-346-2246