Klamath Hall Drilling Noise Advisory 2/02/22

Begin:  Wednesday, February 2nd, 2022 at 5:00 am

End:      Wednesday, February 2nd, 2022 at 3:00 pm

Building(s) or Area(s) Impacted:  Klamath Hall – rooms 019, B026, and B024A

Scope:  For the Klamath Prep room renovation, the contractor will need to drill 4 holes through the concrete floor, for future plumbing routes. Drilling will occur from KLA 019 to KLA B26 and KLA B24A.

Services Impacted:  The users of the immediate spaces have been notified, but all building users should be aware of the noise generated by this drilling.

Work Performed By:  Mortenson Construction

ContactTim Allenbaugh, CPFM Owner’s Representative, 541-346-8214