Begin: Tuesday, September 7th, 2021 at 7:00 am
End: Tuesday, September 7th, 2021 – unknown
Building(s) or Area(s) Impacted: Lock and Key Shop
Scope: Building power will be put on temporary service to support the adjacent ZIRC project.
Services Impacted: Build power.
Work Performed By: Fortis Construction
Contact: Colin Brennan, CPFM Owner’s Representative, 541-346-8242 or 541-654-2972