Volcanology HVAC Shutdown 8/19/21

Previous notice sent – actually 8/19

 

Begin:  August 19th, 2021 at 7:00 am

End:     August 19th, 2021 at 6:00 pm

Building(s) or Area(s) Impacted:  Volcanology

Scope:  Each HVAC unit will be shut down for approximately ½ – 1 day during the timeframe indicated to perform cleaning. This is part of the wildfire insurance response project.

Services Impacted:  HVAC units will be offline for the entire building.

Work Performed By:  ERS, Inc.

Contact:  Adam Jones, SRS Buildings Sciences Manager, 541-346-8397