Begin: Monday, April 12, 2021
End: Friday, April 30, 2021
Building Impacted: 1900 Millrace (formerly the Innovation Center) rooms 109, 116, & 120.
Scope: Asbestos Abatement of existing floors in room 109 & 116. Requires pre/post work to disconnect/reconnect the fume hood in room 120.
- April 12-16: prep work that includes shutdown of fume hood ventilation in rooms 116 & 120, hot work (welding) on West exterior side of the building.
- April 19-21: abatement work in rooms 109 & 116
- April 21-30: post abatement work that includes turning back on the fume hood ventilation & hot work on the West exterior side of the building. The bulk of the work is expected to occur until 4/23, however there could be some minor residual work that lasts until 4/30.
Services Impacted:
- No additional electrical or HVAC disruptions are known at this time. A shut down notice will be issued as necessary.
- Building access will be maintained during construction but may require minor detours.
- Users can expect to hear construction noises like hammering, drilling, grinding, and see Rose City Contracting employees and UO staff entering and exiting the building during normal business hours.
Work performed by: Facilities Construction Services, Rose City Contracting
Contact: Theo Davis, CPFM Design & Construction Project Manager, 541-346-1012