Begin: Monday, November 16th, 2020 – daily 8:00 am to 4:00 pm
End: Tuesday, November 17th, 2020 – daily 8:00 am to 4:00 pm
Building(s) or Area(s) Impacted: Friendly Hall – see below for specific locations affected.
- Panel K: Entire basement.
- Panel D (and sub-panels D1 & D2): Rooms 108, 019, 111, 112, 114, 116, 216, 217, 220, 221, 222. 223, 224, (potentially 215, 225, 226, 227), 308, 312, 313, 315, 316, 318, 319, 324, 325.
- Panel EM1: Hallway & exit lights on all levels, and outside lights.
Scope: Relocation of feeder conduits passing through the new elevator shaft, and adding new feeders into electrical panels D, K, and EM1. The work should be able to be completed in one day, but the contractor would like two days for contingency.
Services Impacted: The contractor will only de-energize one panel at a time – so power in each area noted will not be down an entire day – and they assure power will be restored in all impacted areas by days end.
Special Instructions: Please shut down all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when power is turned back on, a power surge can corrupt the clone files in the machines, and can change preconfigured settings.
Work Performed By: Sunset Electrical and Bridgeway Contracting
Contact: Gene Mowery, CPFM Owner’s Representative, 541-346-5593