Klamath Hall Compressed Air and Natural Gas Shutdowns 1/21/20

1)

Date:  Tuesday, January 21st at 5:00 am until 5:30 am

Scope:  Shutdown of compressed air that will impact the full building. The shutdown is to isolate the phase two renovation area.

Services Impacted:  Compressed air will not be working.

Extra Notes:  Temporary air compressors can be provided and connected as needed.

 

2)

Date:  Tuesday, January 21, 2020 5:00 am to 10:00 am

Scope:  The natural gas shutdown is to isolate renovation areas on both levels two and three.

Services Impacted:  Natural gas will be off throughout the entire building.

 

ContactDenise Stewart, Owner’s Representative, 541-346-2280 or 541-335-1258