The concrete base for the grey courtyard pavers will be poured soon. The pavers have arrived and look great.

Courtyard Paver

Courtyard Paver

Much progress has been made on the elevator.

Elevator

Elevator

An initial pour of the gray concrete that will surround the library on the plaza level has been completed on the south side of the PSC.

Gray Concrete

Gray Concrete

 

The steel pillars along the west-facing side of the building are being polished and look beautiful.

 

Polishing Pillars

Polishing Pillars

 

Polished Pillar

Polished Pillar

 

The courtyard is taking shape. It will be a beautiful and restful place to study once it’s landscaped with native Oregon and Pacific Northwest plants.

Courtyard

Courtyard

Much of the wall framing has been completed (including the cafe!). The base for the service desk is in and the wall for the CIS tutoring room is up as well. Some walls have been roughed in including the wall between the makerspace and the drop-in computer lab.