Begin: Monday, December 23rd, 2019 at 6:00 am
End: Monday, December 23rd, 2019 at 9:00 am
Building(s) or Area(s) Impacted: LISB and Lokey Labs
Scope: Need to modify the piping of the Process Cooling Water (PCW) system in the Willamette basement to benefit two renovation projects.
Services Impacted: The Process Cooling Water will be offline to the Lokey Labs and Lewis Integrative Science Building (LISB) for the three hour duration. This will also impact CT rooms on the 3rd floor of LISB.
Special Instructions: Please shutdown critical equipment connected to the system prior to 12/23 at 6:00 am.
Contact: Denise Stewart, Owner’s Representative, 541-346-2280 or 541-335-1258