Begin: Tuesday, October 28, 2025, at 7:00 am
End: Friday, January 30, 2026, at 4:00 pm
Building(s) or Area(s) Affected: Lewis Integrative Science Building – rooms 009 and 012B
Scope: Labs 009 and 012B will be remodeled:
- October – November – A new Glove Box will be installed in Lab Room 009.
- November – January – A new Glove Box and other equipment will be installed in Lab Room 012B.
Services Impacted:
- October – November – Minimal to no impact to the building or users is expected.
- November – January – Work is expected to be more disruptive, additional notices will be sent out as construction activities commence.
Work Performed By: Luna Design and Construction
Contact: David Mason, CPFM Owner’s Representative, 541-346-5679
Current construction and impacts information can be found on the UO Maps site.