Begin: Friday, April 19, 2024, at 7:00 am
End: Friday, April 19, 2024, at 3:30 pm
Building(s) or Area(s) Affected: Huestis Hall
Scope: The lab exhaust fans will be shut down to install a larger bypass on the penthouse fans.
Services Impacted: Fume hoods and lab exhaust will not be available during this shutdown.
Special Instructions: Fume hood sashes should be closed and containers within the fume hoods sealed prior to this date.
Work Performed By: FM Sheetmetal
Contact: Martina Oxoby, CPFM Owner’s Representative, 541-346-5880
Current construction and impacts information can be found on the UO Maps site.