12/14/22 – 12/16/22 Streisinger Hall Heating System Shutdown

UPDATE 12/15/22: 
Crews are continuing to work on the lines.  They expect to have the heating water restored to the building by noon on Friday, 12/16/22.  An update will be sent when the water has been restored.

 

UPDATE 12/9/22:
The start date for this shutdown has been moved to 12/14/22 and will finish 12/15/22.

 

BeginMonday, December 12th, 2022 at 7:00 am Wednesday, December 14th, 2022 at 7:00 am

End:      Tuesday, December 13th, 2022 at 3:00 pm, Thursday, December 15th, 2022 at 3:00 pm, Friday, December 16th, 2022 at 12:00 noon

Building(s) or Area(s) Affected:  Streisinger Hall

Scope:  The heating system for the 3rd floor of Streisinger Hall will be shutdown for the installation of valve replacements

Services Impacted:  This will shut down the heating service to the 3rd floor and may affect the heating throughout the building.  The heat will be restored end of day on Wednesday, December 14th at 3:00 pm to mitigate the impact overnight if the work is not finished that day, then shutdown again Thursday, December 15th at 7:00 am if needed.

Work Performed By:  CPFM FS Plumbing Crew

ContactJim Cody, CPFM Associate Dir. of Facilities Services, 541-346-2302