Begin: Tuesday, May 3rd, 2022 at 6:00 am
End: Tuesday, May 3rd, 2022 at 4:00 pm
Building(s) or Area(s) Impacted: Klamath (Outage only), Willamette, ONAMI (ISC), LISB (Informational notice)
Scope: As a part of the Huestis Renovation project, a walk-in cooler is being installed in the Prep room (KLA 19), which will require the addition of a new process chilled water (PCW) connection to the existing system. Klamath users will have no PCW during the proposed work. All other buildings utilizing PCW will remain operational during the work
Services Impacted: All Process Chilled Water, (Klamath building wide only)
Special Instructions: . Once work is complete (Tuesday afternoon), building users may notice a slight disruption in services as the Klamath system comes back on line.
Work Performed By: Mortenson Construction
Contact: Tim Allenbaugh, CPFM Owner’s Representative, 541-346-8214