Begin: Monday, April 18th, 2022
End: Friday, April 29th, 2022
Area Impacted: North side of Central Power Station
Scope: Due to cooling tower media fill replacement, a crane will be used to lift material to and from the Chilled Water Plant roof
Services Impacted:
- Little to no impact is expected.
- Large vehicles will be accessing the CPFM Compound.
- The crane will be staged east of the Chilled Water Plant.
Extra Notes: Additional cooling tower media fill will be replaced in May. Dates to be determined.
Work Performed By: Fox Engineering and Northwest Mechanical
Contact: Kyle Wilson, CPFM Utilities Maintenance Manager, 541-346-2246