UPDATE 6/17 at 3:56 pm: The RO water has been restored.
Begin: Wednesday, June 17th, 2020 at 3:30 pm
End: Wednesday, June 17th, 2020 at 5:00 pm
Building(s) or Area(s) Impacted: Streisinger 2nd Floor
Scope: We need to shut down the reverse osmosis water to the second floor to make emergency repairs.
Services Impacted: RO water to the 2nd floor
Work Performed By: CPFM Facilities Plumbing Support
Contact: Ken Straw, CPFM Facilities Mechanical & Plumbing Shop Manager, 541-346-5406