2nd UPDATE 4/6/2020: Please disregard. This shutdown has been cancelled.
UPDATE 4/6/2020: This shutdown has been rescheduled for Saturday, April 25th, 2020
UPDATE 3/24/2020: This project has been postponed due to capacity issues related to the university’s response to COVID-19.
Begin: Thursday, March 26th, 2020 at 6:00 am Saturday, April 25th, 2020 at 5:00 am
End: Thursday, March 26th, 2020 at 3:00 pm Saturday, April 25th, 2020 at 5:00 pm
Building or Area Impacted: Klamath Hall
Scope: Removal and repair of a broken lab waste line in the basement.
Services Impacted:
- All lab sinks, fume hood waste, and any other industrial waste lines for the entire building should not be used.
- The restroom drains will not be affected.
Work Performed By: Lease Crutcher Lewis
Contact: Denise Stewart, CPFM Owner’s Representative, 541-346-2280 or 541-335-1258