Annual Autoclave Steam Generator Preventative Maintenance 3/23/20 – 3/27/20

Begin:  Monday, March 23rd, 2020 at 8:00 am

End:      Friday, March 27th, 2020 at 8:00 am

Buildings Impacted:  Cascade Annex, Columbia Hall, Huestis Hall, Klamath Hall, Lewis Integrative Science Building (LISB), Onyx Bridge, Pacific Hall, Streisinger Hall, University Health, Counseling, and Testing Center, Volcanology, Willamette Hall, and ZIRC

Scope:  CPFM Utilities and Energy will be performing the annual preventative maintenance and an internal inspection of the autoclave steam generator March 23 – 27, 2019.

Services Impacted:  The autoclave steam heat exchanger will be shut down. Clean steam will be unavailable.

Extra Notes:  Chemical treated 60 psi steam will be cross connected and provided for the duration of the shutdown.

Work Performed By:  CPFM Utilities and Energy with a Contractor

ContactKyle Wilson, CPFM Utilities Maintenance Manager, 541-346-2246