The new men’s and women’s restrooms downstairs in the academic commons now have roughed in walls (the one restroom upstairs in the social commons will be gender-neutral). The elevator should be finished by mid-April. The roof should be completed by the end of March. The atrium is currently being excavated, including digging channels for plumbing and electricity. Steel pillars are being covered with fire-resistant paint.