6/20/23 – 7/10/23 Knight Library Second Floor South Reading Room Construction Work Advisory

Begin:  Tuesday, June 20, 2023

End:      Monday, July 10, 2023

Building(s) or Area(s) Affected:  Knight Library

Scope:  Demolition of counters and buildouts around four columns, plus minor electrical work, will take place in the 2nd floor South Reading Room.

Services Impacted:  Noise and odor can be expected during this time.

Work Performed By:  CPFM Facilities

ContactBrianna Liberty, CPFM D&C Design Associate, 541-346-7612 or 541-556-9618

Current construction and impacts information can be found on the UO Maps site.

Image of Knight Library 2nd floor South Reading Room

5/04/23 UOPD West University Station Possible Electrical Outage

Begin:  Thursday, May 4, 2023

End:      Thursday, May 4, 2023

Building(s) or Area(s) Affected:  UOPD West University Station

Scope:  EWEB will be doing work in the area this evening and there is the possibility the West University Station may lose power.

Services Impacted:  Potential for electrical outage.

Special Instructions:  Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.  For questions, please contact Kati Kronholm at 541-346-5370 or katik@uoregon.edu.  For non-copier questions, please reach out to the contact person listed below.

Work Performed By:  EWEB

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Image of UOPD West University Station

4/24/23 – 8/31/23 Fenton Hall Room 314 Construction Work Advisory

UPDATE 7/06/23:
Due to renovations on the top floor of Fenton Stacks, the fire sprinkler system will need to be shut down for alterations on Thursday, July 20th, from 6:00 am to 5:00 pm.  Work will take place in room 314 but the shutdown will affect the entire building.  The contractors involved are GB Construction and Harvey & Price.

Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

 

UPDATE 6/28/23:
Due to alterations to the upper level of the Fenton Stacks (room 314), the network cables will need to be relocated on Monday, July 10th, from 7:00 am to 4:00 pm.  This will involve some down-time for UO network cables and Wi-Fi access in Fenton 314, 214, and 114. This outage should not affect the main Fenton building users, but will affect the library stacks.

 

Begin:  Monday, April 24, 2023, at 7:00 am

End:      Thursday, August 31, 2023, at 5:00 pm

Building(s) or Area(s) Affected:  Fenton Hall

Scope:  Fenton Hall room #314 (upper floor of the stacks) will be converted to office space. Starting the week of 4/24/23, GBC Construction will be on site performing demolition, adding new HVAC components, and building new walls within the space. Construction is scheduled to continue through August. Additional updates may be published for specific noise events or building system shutdowns.

Services Impacted:  Building users in adjacent spaces may hear general construction noise, and elevator may be used to facilitate transportation of certain materials.

Work Performed By:  GBC Construction

ContactTim Allenbaugh, CPFM Owner’s Representative, 541-346-8214

Current construction and impacts information can be found on the UO Maps site.

Image of Fenton 314

4/17/23 UO Annex Planned Power Outage

Begin:  Monday, April 17, 2023, at 2:00 am

End:      Monday, April 17, 2023, at 8:00 am

Building(s) or Area(s) Affected:  UO Annex

Scope:   EWEB will shut down the electrical power to complete work on the power lines and poles in the 12th Avenue alley between Alder and Kincaid.

Services Impacted:  Power will be offline during this time.

Special Instructions:  Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.  For questions, please contact Kati Kronholm at 541-346-5370 or katik@uoregon.edu.  For non-copier questions, please reach out to the contact person listed below.

Work Performed By:  EWEB

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.Image of UO Annex and the 12th Ave. alley between Alder and Kincaid.

4/04/23 – 4/07/23 Ford Alumni Center Light Construction Work Advisory

Begin:  Tuesday, April 4, 2023

End:      Friday, April 7, 2023

Building(s) or Area(s) Affected:  Ford Alumni Center

Scope:  Light construction work (electrical, removal/installation of wall mounted items, painting) happening in 201 and in hallway outside of 209F.

Services Impacted:  Noise and odor can be expected during this time.

Work Performed By:  CPFM Facilities

ContactBrianna Liberty, CPFM D&C Design Associate, 541-346-7612 or 541-556-9618

Current construction and impacts information can be found on the UO Maps site.

Image of Ford Alumni room 201 and hallway by 209F

3/23/23 UO Annex Planned Power Outage

Begin:  Thursday, March 23, 2023, at 9:oo am

End:      Thursday, March 23, 2023, at 11:00 am

Building(s) or Area(s) Affected:  UO Annex

Scope:  EWEB will perform an electrical shutdown at the UO Annex to change out a transformer for the construction project going on in the alley behind the building.

Services Impacted:  Power will be offline during this time.

Special Instructions:  Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.  For questions, please contact Kati Kronholm at 541-346-5370 or katik@uoregon.edu.

Work Performed By:  EWEB

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

 

3/25/23 Huestis Hall Basement and Lokey Labs Electrical Outage

Begin:  Saturday, March 25, 2023, at 7:00 am

End:      Saturday, March 25, 2023, at 4:00 pm

Building(s) or Area(s) Affected:  Huestis Hall Basement and Lokey Labs

Scope:  As part of the Huestis Hall Renovation project, there will be a power outage affecting Huestis Basement and Lokey Labs.  Lokey Labs standby power via panel 4A1, Huestis Basement normal power via panels 4L1, BN1-4, BN2-4.

Services Impacted:  This will affect lab exhaust fans 1 and 2, AHU 1 and 2 and the fire alarm system in the Huestis Basement. Glass and rack washers will also be offline.

Special Instructions:  Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.  For questions, please contact Kati Kronholm at 541-346-5370 or katik@uoregon.edu.

Additional Instructions:  Fume hood sashes should be closed and containers within the fume hoods sealed prior to this date.

Work Performed By:  EC Electric, Lewis Construction

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Current construction and impacts information can be found on the UO Maps site.

4a1 4.0 shutdown Huestis Existing 1 line

4A1 shutdown 4.0 Basement Power E1.20 and E1.21

3/29/23 Campus Wide Island Mode Testing

UPDATE:
Island Mode testing has been completed for the day.

 

CPFM Utilities and Energy is scheduling Island Mode testing for Wednesday, March 29th between the hours of 8:00 am and 1:00 pm.  The date was moved to Wednesday, March 29th following feedback from campus partners.

The Island Mode testing will follow-up on the December failure to determine the root cause of the problem. The island mode procedure will be attempted several times throughout the scheduled test period.  As a result, short duration power outages may occur at any time throughout the testing period.  Utilities and Energy will have engineers who designed the equipment and service technicians onsite to assist us in determining the cause of the failure.  The electrical distribution system redundancy and resiliencies depend upon the properly functioning power generation system and island mode capabilities.

The Utilities and Energy would like to thank the campus community with the timely feedback and being flexible for this critical testing.

Special Instructions:  Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.  For questions, please contact Kati Kronholm at 541-346-5370 or katik@uoregon.edu.

Work Performed By:  CPFM Utilities & Energy

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

10/24/22 POSTPONED – Huestis, Willamette, and Streisinger Halls Electrical Shutdown

UPDATE:
This work is delayed and will not occur on 10/24.  The Shutdown Notice will be rescheduled.

 

BeginMonday, October 24, 2022, at 7:30 am postponed

End:   Monday, October 24, 2022, at 8:30 am postponed

Buildings:  Huestis, Willamette, and Streisinger Halls

Scope: As part of the Huestis Renovation project there will be a brief electrical shutdown affecting service to the steam condensate pump, AHU 1 and 2, glass and rack washer in room 005 and RO pump service to Streisinger and Willamette.

Services Impacted: Campus Heating System, Electrical, HVAC Air Supply, RO/DI Water, Steam/Condensate will be impacted.

Work Performed By: Lease Crutcher Lewis and EC, Siemens

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

To view current construction and impacts. visit UO Map.

3/27/23 – 9/11/23 Prince Lucien Campbell ‘Heritage Project’ Surge Work Advisory

UPDATE 8/31/23:
Prior to completion of our classroom upgrade projects in rooms 72 and 184, our contractors need to perform some audible fire alarm testing. There will be a pre-test on September 5th between 6am and 8am, and a city fire alarm inspection on September 11th between 6am-8am. Both days may involve both audible alarms and lighted strobes during the specified times.

Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

 

UPDATE 8/25/23:
Due to electrical conduit installation in room 72, there will some loud actively in an around that space. Anchors will be set into existing concrete ceiling, using powder actuated fasteners. This sounds similar to a fire cracker when discharged. Ongoing work this Friday 8/25 through Tuesday 8/29.

 

UPDATE 8/01/23:
For new ceiling grid installation, seismic cabling will need to be installed into the concrete ceiling in room 72.  This will include powder actuated fasteners.  This work is quite loud and can sound like a firecracker.  We anticipate this noise to continue (off and on) between Thursday, August 3rd, and Wednesday, August 9th, which will affect the surrounding rooms, especially room 175.

 

UPDATE 7/21/23:
Due to ongoing construction for the Heritage Surge projects, there will be activities with elevated noise levels in room 72 on July 24th and 25th, affecting the surrounding areas.  Additionally, the remodel completion date has been revised to the end of August.

 

UPDATE 4/24/23:
This is short notice, but I have been notified that our contractor has some concrete drilling to perform tomorrow, Tuesday 4/25, in room 72.  Drilling will create noise in adjacent spaces between 6:00 am and 12:00 noon.

 

Begin:  Monday, March 27, 2023, at 7:00 am

End:      July 15, August 31, Monday, September 11, 2023, at 8:00 am

Building(s) or Area(s) Affected:  Prince Lucien Campbell rooms 72, 184, plus adjacent rooms

Scope:  As part of the Heritage Project “Surge” effort, rooms 72 and 184 will be renovated between 3/27 and 7/15. We will provide additional project updates that may be useful to building occupants, as we schedule construction activities.

Services Impacted:

  • There will be general construction noise and odor throughout the construction duration, but our team will target the most intrusive or loud activities for times less likely to disrupt daily scheduled events.
  • The bulk of the demolition work is scheduled for Spring Break.
  • This will affect different systems at different times in these areas, including heating, electrical, fire alarm system, and HVAC air supply.

Work Performed By:  GBC Construction

ContactTim Allenbaugh, CPFM Owner’s Representative, 541-346-8214

Current construction and impacts information can be found on the UO Maps site.

3/27/23 – 9/15/23 McKenzie Hall ‘Heritage Project’ Surge Work Advisory

UPDATE 9/01/23:
Start time for the September 7th fire panel test will be 7:00 am with expected completion by 8:00 am.  Alarm sound will be intermittent during this period of time.

 

UPDATE 8/28/23:

The end date has been extended to September 15th to complete a few required activities, including a fire panel test.

The fire panel test will take place on September 7th.  Fire panel sounders will be set off causing loud noise for a short period of time.

Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time and alarms that occur after the scheduled time should be considered real events and occupants should evacuate as usual per the U of O Emergency Procedures.

If there are questions regarding emergency evacuation, please visit Emergency Management & Continuity, https://safety.uoregon.edu/evacuations

 

UPDATE 8/15/23:
The end date has been extended to Friday, September 1st.

 

UPDATE 7/21/23:
Expect construction noise on July 24th and 25th that is louder than is typically heard.  Additionally, remodel completion date has been revised with expectation of completion on August 11th.

 

UPDATE 6/09/23: 
On Monday, June 26th, from 7:00 am to 3:00 pm, network cabling will be pulled and rerouted for this project.
This will impact rooms 101, 101A, 201, 214, and 215.
Work will be performed by UO Information Services, GBC Construction, and New Way Electric.

 

Begin:  Monday, March 27, 2023, at 7:00 am

End:      July 15, August 11, Friday, September 1  15, 2023, at 5:00 pm

Building(s) or Area(s) Affected:  McKenzie Hall rooms 101, 101A, plus adjacent rooms & hallways

Scope:  As part of the Heritage Project “Surge” effort, rooms 101 and 101A will be renovated between 3/27 and 7/15. We will provide additional project updates that may be useful to building occupants, as we schedule construction activities.

Services Impacted:

  • There will be general construction noise and odor throughout the construction duration, but our team will target the most intrusive or loud activities for times less likely to disrupt daily scheduled events.
  • The bulk of the demolition work is scheduled for Spring Break.
  • This will affect different systems at different times in these areas, including heating, electrical, fire alarm system, and HVAC air supply.

Work Performed By:  GBC Construction

ContactGene Mowery, CPFM Owner’s Representative, 541-346-5593

Current construction and impacts information can be found on the UO Maps site.

3/16/23 Thompson University Center Electrical Outage

Begin:  Thursday, March 16, 2023, at 12:00 midnight

End:      Thursday, March 16, 2023, at 4:00 am

Building(s) or Area(s) Affected:  Thompson University Center

Scope:  EWEB will be shutting the power off early Thursday morning. They need to tap a feeder from the pole outside TUC to the construction site down the street.

Services Impacted:  Electricity will be down during this time.

Special Instructions:  Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.  For questions, please contact Kati Kronholm at 541-346-5370 or katik@uoregon.edu.

Work Performed By:  EWEB

ContactMelinda Seeley, CPFM Campus Planning, Real Estate Property Specialist, 541-346-5550

Current construction and impacts information can be found on the UO Maps site.

3/03/23 Lewis Integrative Science Building Rooms 142, 145 -152 Electrical Shutdown

Begin:  Friday, March 3, 2023, at 7:00 am

End:      Friday, March 3, 2023, at 10:00 am

Building(s) or Area(s) Affected:  Lewis Integrative Science Building – Rooms affected per drawing: 142, 145, 146, 147, 148, 149, 150, 151, 152

Scope:  CPFM Facilities crew will replace a relay in the mezzanine.  Power will be shut off to CKT#10 in PNL BN2-4 (located in basement), which supplies lighting to multiple rooms – see attachment for details.

Services Impacted:  Power will be off during this time.

Work Performed By:  CPFM FS BAS Dept.

ContactWork Control Center, Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

2/18/23 Huestis Basement and Lokey Labs Electrical Shutdown

UPDATE:
The shutdown was not able to be completed as scheduled.  The work described below has been rescheduled for Saturday, February 18.

 

Begin:  Saturday, February 04  18, 2023, at 7:00 am

End:      Saturday, February 04  18, 2023, at 12:00 noon

Building(s) or Area(s) Affected:  Huestis Basement and Lokey Labs

Scope:  As part of the Huestis Hall Renovation project, normal power will be offline for installation of temporary power j-boxes and electrical conduit reconfiguration in the Huestis basement. The shutdown of the 600 amp disconnect will temporarily shut down normal power to all Lokey Labs systems on panel 2N2 including heating water, and all Huestis Basement systems on panels Bn3-2, Bn4-2, Bn5-2, and Bn6-2.

Per previous shutdowns to these panels, it was determined that critical equipment is on standby power.

Services Impacted:

  • This will affect the electrical, fume hoods, heating systems, chilled water, and exhaust.
  • The work is scheduled for 5 hours on Saturday, but the shutdown is not expected to take the full duration.

Special Instructions:  Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.

Additional Instructions:  Fume hood sashes should be closed and containers within the fume hoods sealed prior to this date.

Work Performed By:  EC and Lewis

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

Current construction and impacts information can be found on the UO Maps site.

Temp power shutdown 600a Basement Power E1.20 and E1.21 (1)

1/03/23 Klamath Hall Electrical Panel Shutdown

UPDATE:
Power was restored to Klamath Hall.  All electrical is back in normal status.

 

UPDATE:
The Onyx Bridge east elevator will also be down during this time.

 

Begin:  Tuesday, January 3rd, 2023, at 9:00 am

End:      Tuesday, January 3rd, 2023, at 1:00 pm

Building Affected:  Klamath Hall

Scope:  The main electrical panels will be shut down to evaluate components and test breakers after water intrusion that occurred on 12/10/22.

Services Impacted:  This will affect the electrical power, exhaust, fume hoods, heating, HVAC Air Supply, lab vacuum, and elevator.

Special Instructions:

  • Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.
  • Fume hood sashes should be closed and containers within the fume hoods sealed prior to this date.

Work Performed By:  Outside Contractor

ContactWork Control Center, Campus Planning and Facilities Management, 346-2319

To view current construction and impacts. visit UO Map.

12/27/22 – 12/30/22 Knight Library #57, 19, H57 Renovation Advisory

Begin:  Tuesday, December 27th, 2022

End:      Friday, December 30th, 2022

Building(s) or Area(s) Affected:  Knight Library Rooms 19, 57, and Hallway H57

Scope:  Abatement, demolition, and renewal will occur for rooms 19, 57, and hallway H57, while they receive new lighting, flooring, paint, and electrical.

Services Impacted:

  • ADA access will be impacted from the NW lower entrance to the elevator.
  • Construction noise and odor can be expected during this time.

Work Performed By:  PMG Demolition and CPFM Facilities Services

ContactJanell Cottam, CPFM Owner’s Representative, 541-346-7536

Current construction and impacts information can be found on the UO Maps site.

12/20/22 Campus Planned Power Testing Unexpected Service Interruption

During island mode testing, we operated a seamless transition from the EWEB power grid to Island Mode.  However, at 11:09 am, while transitioning from Island Mode back to the main grid, we experienced an unexpected momentary glitch in the system.  We are now back on stable power and will have no further testing today.  We will continue to troubleshoot the system at a future date.

We apologize for the inconvenience this has caused.  Please verify that your equipment is back up and operating as expected.

Should you need to report any issues, contact Work Control Center at 541-346-2319 or workcontrolcenter@uoregon.edu.

Current construction and impacts information can be found on the UO Maps site.

12/20/22 Campus Planned Power Testing

Begin:  Tuesday, December 20th, 2022, at 7:00 am

End:      Tuesday, December 20th, 2022, at 3:30 pm

Building(s) or Area(s) Affected:  Campus Wide

Scope:  Utilities and Energy (U&E) will start testing Island mode quarterly instead of annually. This emergency power system requires extensive service more often and complies with our service agreement with the turbine manufacturer. These tests will be during Spring break, Summer break, the annual September power testing, and Winter break. The next test will be December 20th, 2022. Most likely we will enter island mode throughout the day for testing with no exact timeframe.

Services Impacted:  This is a seamless power transition and we do not expect any impacts to campus power.

Special Instructions:  Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.

Work Performed By:  Utilities & Energy and Contractor

ContactRick Tabor, CPFM Interim Co-Dir Utilities & Energy, 541-346-7511

To view current construction and impacts, visit UO Map.

12/19/22 Feeder 1 Electrical Shutdown

Begin:  Monday, December 19th, 2022, at 7:00 am

End:    Monday, December 19th, 2022, at 8:00 am

Buildings:  Unthank Hall, Bean Hall, Global Scholars, Kalapuya Ilihi, Ford Alumni, Matt Knight Arena.

Scope:  Feeder 1 will be shut down to connect the HWTP Phase 2 Project to campus power.

Services Impacted:

  • This will affect main power and elevators, however these buildings will be on standby power during this time.
  • This will not impact Hayward Field.

Special Instructions:  Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.

Work Performed By:  Oregon Electric Group and CPFM U&E

ContactGeorge Bleekman, CPFM Owner’s Representative, 541-346-2625

Current construction and impacts can be found on the UO Maps site.

12/12/22 – 1/31/23 PLC Classroom Construction Noise Advisory

Begin:  Monday, December 12th, 2022

End:      Tuesday, January 31st, 2023

Building(s) or Area(s) Affected:  Prince Lucien Campbell Hall Rooms 348, 353, and adjacent rooms

Scope:  PLC 348 and 353 will be renovated into a single classroom

Services Impacted:  Most construction activity will be restricted to the interior of the two rooms however, some construction related noise can be expected in adjacent areas.  The bulk of the work will take place over the winter break, with less intrusive work continuing into the first weeks of winter term.

Work Performed By:  GBC Construction

ContactTim Allenbaugh, CPFM Owner’s Representative, 541-346-8214

Current construction and impacts information can be found on the UO Maps site.

12/10/22 Unexpected power outage impacting Klamath Hall and Onyx Bridge

UPDATE – #2 12/10/22 at 6:05 pm:

The power has been restored. Power is on in a single-ended condition. Power is currently being fed from feeder 10.

A contractor will be out as soon as Utilities and Energy can get them to campus to evaluate the switch.

UPDATE – 12/10/22 at 4:44 pm:

The power outage has been determined to impact all floors of Klamath Hall, including fume hoods.  Facilities and Utilities and Energy are on site. EH&S is aware and working with CPFM personnel. The Utilities and Energy Electrical supervisor is on site. The hope is to have the power restored in 3-4 hours.  The Building Automation (BAS) and Mechanical Teams are on site, ready to support the restore.

INITIAL EVENT NOTICE 12/10/22 at 2:08 pm: 

Parts of Klamath Hall and Onyx Bridge lost electrical power today (December 10). This resulted in various security and other alarms being triggered. UOPD responded to ensure the security of the facility, and Facilities Services electricians are onsite for assessment and restoration of the power situation.

The power outage is currently impacting the following:

  • Klamath Hall Basement, 1st and part of 2nd Floor
  • Onyx 1st Floor

The restore ETA is still TBD, but teams hope to achieve a power restoration by evening hours today. A restore message will be sent as soon as services are restored.

11/29/22 Pine Mountain Observatory Electrical Outage

Begin:  Tuesday, November 29th, 2022 at 10:00 am

End:      Tuesday, November 29th, 2022 at 3:00 pm

Building(s) or Area(s) Affected:  Pine Mountain Observatory

Scope:  There will be a planned power outage to allow Central Electric to do some system improvement work at their Hampton Substation.

If temperatures will be below freezing, the outage will be cancelled and rescheduled at a later date.  A call will be placed notifying Pine Mountain if the outage is taking place as scheduled or if it has been cancelled.

Services Impacted:  Power is expected to be offline for approximately 5 hours.

Special Instructions:  Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.

Work Performed By:  Central Electric Cooperative, Inc.

Contact:  Brent ten Pas, Director of Member Services and Public Relations 541-548-2144

Information on current construction and impacts can be found at UO Maps

10/13/22 Zebrafish International Resource Center Electrical Outage

Begin:  Thursday, October 13th, 2022, at 7:00 am

End:      Thursday, October 13th, 2022, at 7:30 am

Building(s) or Area(s) Impacted:  Zebrafish International Resource Center

Scope:  Building power will be offline for 30 minutes to install an electric meter .

Services Impacted:  This will impact electrical power, exhaust, and the HVAC air supply.

Special Instructions:  Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.

Work Performed By:  Fortis Construction

ContactColin Brennan, CPFM Owner’s Representative, 541-346-8242 or 541-654-2972

9/24/22 Huestis Hall Basement and Lokey Labs Electrical Shutdown

REVISED:
The shutdown has been rescheduled for Saturday, September 24th, 2022.

 

Begin:  Saturday, September 10th, September 24th, 2022 at 6:00 am

End:      Saturday, September 10th, September 24th, 2022 at 4:00 pm

Building(s) or Area(s) Affected:  Huestis Hall Basement and Lokey Labs

Scope:  Permanent shutdown of Huestis main distribution panel (MDP) to allow buildout of new construction equipment. Re-distribute power to 2N2A, BN-7, Construction temp power, and OC-2 loads from 3) new 600A fused switches to be located in transformer vault behind MDP. – see attachments

Services Impacted:  Normal power will not be available during this shutdown. Standby power will not be affected.

Special Instructions:  Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.

Work Performed By:  Lease Crutcher Lewis and EC

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

To view current construction and impacts. visit UO Map.

E6.13 MDP demo schematic (1) (002)

MDP distribution plan REV2

Temp power SQD H326NR (1)

9/22/22 Huestis Basement Zebrafish Facility Electrical Shutdown

Begin:  Thursday, September 22nd, 2022 at 6:00 am

End:      Thursday, September 22nd, 2022 at 7:00 am

Building and Area:  Huestis

Scope: As part of the Huestis Hall Renovation Project, power will be shut off to the Huestis basement Zebrafish Facility for 1 hour to allow temp power to be removed from BS1-2 and install the permanent feed. Siemens will monitor equipment alarms in Aquaculture room 03.

Services Impacted:  Electrical will be offline in the Huestis basement Zebrafish Facility.

Special Instructions:  Please shut down and unplug all multi-function copier devices as well as any printers during scheduled power outages. The software on these machines can be negatively affected due to the power surge when the power is turned back on.  A power surge can corrupt the clone files in the machines and change preconfigured settings.

Work Performed By:  Lease Crutcher Lewis and EC

Contact: Martina Oxoby, CPFM Owner’s Representative, 541-346-5880

To view current construction and impacts. visit UO Map.