5/13/22 – 12/31/22 Volcanology Steam Heat Shutdown

UPDATE:  The new  steam heat pipeline has been active since December.

 

UPDATE:  A walkthrough with contractors has been completed, we are now working through proposals, ordering parts, and setting up equipment to prepare for excavation in order to install a new pipeline and return heat to the building.  The timeline for completion is unknown at this time.

Begin:  Friday, May 13th, 2022 at 12:00 noon

End:    Estimated around Friday, September 30th, 2022  TBD Completed in Dec. 2022

Building(s) or Area(s) Impacted:  Volcanology

Scope:  Due to a steam leak on an inaccessible pipe, steam heat will be turned off to the building. The building heat will remain off until pipe excavation and repairs can be completed.

Services Impacted:  The building heat will be off to the east side and in basement room 011A.

Work Performed By:  Contractor

ContactKyle Wilson, CPFM Utilities Maintenance Manager, 541-346-2246