Begin: Friday, October 3, 2025 – unknown
End: Friday, October 3, 2025 – unknown
Building(s) or Area(s) Affected: UO Portland Campus Center Building
Scope: A new dedicated breaker will be installed and power run from the electrical panel in room 212 to an outlet on the west wall in room 200.
Services Impacted:
- Minimal disruption of power in room 200 to cut loose the outlet receiving new dedicated power.
- Electricians will be on ladders to gain access to the ceiling cavity in order to run new wiring from the panel to the outlet – ladder and ceiling access will be in both rooms 212 and 200.
- There may be debris from the ceiling tiles being moved, furniture may be temporarily moved out of the way for access.
Work Performed By: EC Electric
Contact: Melissa Moshofsky, CPFM Owner’s Representative, 541-346-3712
Current construction and impacts information can be found on the UO Maps site.