Begin: Wednesday, August 13, 2025 at 9:00 am

End:     Tuesday, August 19, 2025 at 4:00 pm

Building(s) or Area(s) Affected: Millrace Drive, Garden Avenue, and Villard Street

Scope: EWEB Water Engineering is working on the design for a transmission main on Millrace Drive, Garden Avenue, and Villard Street.  They will be working with a contractor to pothole crossing utilities for project design.  Work is expected to take 3-5 business days to complete.

Services Impacted: Access to UO buildings and parking areas along this route may be temporarily impacted but traffic interruptions should be minimal.

Work Performed By: EWEB and Professional Underground

Contact: Work Control Center, UO Campus Planning and Facilities Management, 541-346-2319

Current construction and impacts information can be found on the UO Maps site.

Millrace impacts outlined on the map