Riverfront Parkway Southbound Lane Closure 5/22/23

Begin:  Monday, May 22, 2023, at 6:00 am

End:      Monday, May 22, 2023, at 6:00 pm

Building(s) or Area(s) Affected:  Riverfront Parkway

Scope:  Riverfront Parkway’s southbound lane at Millrace Drive will be shut down to prepare for future tower crane installation.

Services Impacted:

  • Riverfront Parkway, Knight Campus Building 1, Millrace Parking Garage & buildings on Millrace Drive will be affected – See attached detour plan.
  • The northbound lane will remain open.

Work Performed By:  Hoffman Construction

ContactDenise Stewart, CPFM Owner’s Representative, 541-346-2280 or 541-335-1258

Current construction and impacts information can be found on the UO Maps site.