12/12/22 – 12/15/22 Willamette, Klamath, LISB, and Lokey Labs Processed Chilled Water Shutdown

UPDATE 12/14/22:
The system is currently online and running in it’s designed emergency mode, circulating city water.  On Thursday morning 12/15/22 the system will be placed back into normal operating mode.  A contractor will be testing and adjusting the system water flows 12/20/22 – 12/22/22 but they will not impact the operation of the system or cause any shutdowns.

 

UPDATE 12/13/22:
TAB contractors will be onsite 12/20/22 – 12/22/22 to test and adjust the system.  They will be accessing all rooms with process water manifolds.

 

UPDATE 12/12/22:
CPFM will be coming through each lab that has a process water connection to ensure that the valves are in the correct position for flushing the system.  This work should take place Tuesday and Wednesday afternoons of this week.

 

Begin:  Monday, December 12th, 2022

End:      Friday, December 16th, 2022  Thursday, December 15th, 2022

Building(s) or Area(s) Affected:  Willamette, Klamath, Lokey Labs, LISB

Scope:  The processed chilled water system will be shut down for work associated with improving system operation and redundancy.

Services Impacted:  All equipment connected to system should be disconnected until construction is complete and the water has been flushed.

This will affect:

  • Willamette: Rooms 39, 41C, 42, 74C, 154, 242, 255, 256, 272, 273
  • Klamath: Rooms 61B, 62, 63
  • LISB: 003, 004A, 004B, 004C, 004D, 018, 201E
  • Lokey Labs: 053A, 063, 073, 073A, 080, 083A, 083A, 087A, 096A, 097A

Work Performed By:  S2 Industrial

ContactKevin Waldrop, CPFM Facilities Engineer, 541-346