Begin: Monday, October 17th, 2022 at 7:00 am
End: Tuesday, October 18th, 2022 at 5:00 pm
Building(s) or Area(s) Affected: Lawrence Hall rooms 106, 107C, and associated hallway
Scope:
- A contractor will be both cutting and draining pipes, as well as core drilling within the Lawrence Hall office spaces shown as highlighted (see diagram below).
- Core drilling will occur between the hours of 8:00 am and 10:00 am on 10/17/22. Construction noise will occur intermittently during this time.
- While pipe draining occurs be advised that the contractor will be removing water from the space and a hose running to the nearest drain may be required. The hose, if required, will be protected with cones and markers to isolate it’s run from general office traffic however, being aware of your surroundings during this time is encouraged.
Services Impacted: No significant service interruptions are expected
Work Performed By: Phoenix Mechanical / Harvey and Price
Contact: Damon Rutherford, CPFM D&C Owner’s Representative, 541-346-8285
To view current construction and impacts. visit UO Map.