8/16/22 – 9/30/22 Lawrence Hall Glass Curtain Replacement and Access Advisory

UPDATE:  9/21/22 – The glass curtain wall has been installed however the exterior concrete needs to be cleaned and sealed and the interior stairwell painted.  The exterior work should be completed mid week next week and the interior work by end of week, 9/30/22.

UPDATE:  8/29/22 – Due to the ongoing work to replace the window curtain wall in the West Stair Tower of Lawrence Hall, the sidewalk between Lawrence and Allen Halls will be closed 8/31/22 – 9/2/22 during working hours only

Begin:  Tuesday, August 16th, 2022

End:      Thursday, September 22nd, 2022

Building(s) or Area(s) Affected:  Lawrence Hall and sidewalk coming from E. 13th Ave.

Scope:  The glass curtain walls on the stair tower on the west side of Lawrence Hall are being replaced.  Demolition has been ongoing and replacement work will begin next Tuesday.

Services Impacted:

  • The stairwell on the west side of Lawrence Hall will be closed for the duration of the project.
  • Interior signage will be placed to show alternative egress.
  • Access through the exterior door at the base of the stairs will be largely maintained but could see temporary closures.
  • Materials will be brought to the site from 13th Street on the sidewalk along Friendly and Allen Hall.

Work Performed By:  Andersen Construction

ContactLuke Helm, CPFM Owner’s Representative, 541-346-8216

To view current construction and impacts. visit UO Map.