DATE REVISED:
This shipment was delayed and is now expected to arrive tomorrow, February 23rd.
Begin: Thursday, February 17th, 2022 Wednesday, February 23rd, 2022
End: Friday, February 25th, 2022 Friday, March 4th, 2022
Building(s) or Area(s) Impacted: CPFM Warehouse and Compound
Scope: A shipment of owner furnished owner installed (OFOI) aquaculture equipment is expected to arrive on 2/17 2/23. Shipment will arrive on a flatbed and be moved into the ZIRC expansion area by Fortis. The move in is expected to take up to 5 days. Components that are vulnerable to cold temps are planned to be staged in the CPFM Warehouse (Bldg. 130).
Services Impacted: Staging will take place in Bldg. 130 in the breezeway (H109).
Work Performed By: Colin Brennan and Fortis Construction
Contact: Colin Brennan, CPFM Owner’s Representative, 541-346-8242 or 541-654-2972