Huestis and Willamette Pathway Closure and Geotechnical Drilling Advisory 1/5/22

Begin:  Wednesday, January 5th, 2022 at 9:00 am

End:      Wednesday, January 5th, 2022 at 4:00 pm

Building(s) or Area(s) Impacted:  Area between Huestis and Willamette (see pic below)

Scope:  As part of Huestis Renovation Project, geotechnical drilling will occur in the lawn between Huestis and Willamette Halls.

Services Impacted:  The north-south pathway from 13th to the Streisinger Courtyard will be closed during this activity.

Work Performed By:  GRI

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880