ADDITIONAL INFORMATION REQUESTED:
We need to find out if there is any equipment that relies on a constant supply of RO water.
If so, what is the building and room number?
We want to be sure that upon restarting the system there isn’t a pressure surge on those pieces of equipment.
Begin: Wednesday, December 29th, 2021 at 7:00 am
End: Thursday, December 30th, 2021 at 10:00 pm
Building(s) or Area(s) Impacted: Huestis, Streisinger, Lokey Labs, LISB, Klamath, Willamette, Onyx Bridge, and Pacific Halls.
Scope: As part of phase 1 work for the Huestis Hall Renovation Project, the entire RO system be temporarily shut down for 48-hours in the Science Complex. This will allow for the installation and testing of isolation valves on the RO lines serving each building.
Services Impacted:
- The RO supply will not be available in Huestis, Streisinger, Lokey Labs, LISB, Klamath, Willamette, Onyx Bridge, and Pacific Halls.
- This shutdown will disable all individual RO faucets, including any in fume hoods.
- All potable (drinking) and industrial water faucets will still be in service, including safety showers and eyewashes.
Work Performed By: Mortenson Construction
Contact: Martina Oxoby, CPFM Owner’s Representative, 541-346-5880