Esslinger Hall Surge Space Construction Advisory 11/11/21 – 5/20/22

UPDATE 4/29: There is still some punch list work to complete. The end date is extended to 5/20.

Begin:  Thursday, November 11th, 2021

End:      Friday, April 29th, 2022 May 20th, 2022

Building(s) or Area(s) Impacted:  Esslinger Hall – Rooms 112, 116, 122, 160, 156A, and 166.

Scope:  Due to the Huestis deferred maintenance project, selective areas within Esslinger Hall will be under construction to provide “surge” space for those displaced out of Huestis Hall.

Services Impacted:

  • The noisiest activities will occur before 8am or after 5pm, but general construction activity will be occurring during business hours, through May of 2022.
  • Areas that will be affected are domestic hot and cold water, electrical, exhaust, fire alarm systems, and the HVAC air supply.
  • Updates to this notice will be submitted for specific activities that may have a further impact on building users.

Work Performed By:  Mortenson Construction

Contact:   Tim Allenbaugh, CPFM Owner’s Representative, 541-346-8214