PLC, Condon, Tykeson, and Chapman Hall Steam Heat Shutdown 7/13/21 – 7/14/21

Begin:  Tuesday, July 13th, 2021 at 7:00 am

End:      Wednesday, July 14th, 2021 at 4:00 pm

Building(s) or Area(s) Impacted:  Prince Lucien Campbell, Condon, Tykeson, and Chapman Hall

Scope:  The steam will be shut down in order to remove a leaking section in the 8-inch main utility steam pipe.  A new pipe piece and new 8 inch valve will be installed by a contractor.  A generator and welder will be used above the utility tunnel maintenance hatch to repair the steam pipe.

Services Impacted:  The steam heat will off-line during this time.

Work Performed By:  S2 Industrial

ContactKyle Wilson, CPFM Utilities Maintenance Manager, 541-346-2246