Clean Steam Shutdown 4/20/21

UPDATE 4/20: The autoclave clean steam heat exchanger is back online. Please allow 4-8 hours for the chemical treated steam to work its way out of the pipeline.

Begin:  Tuesday, April 20th, 2021 at 6:00 am

End:      Tuesday, April 20th, 2021 at 1:00 pm

Building(s) or Area(s) Impacted:  Cascade Annex, Columbia Hall, Huestis Hall, Klamath Hall, Lewis Integrative Science Building (LISB), Onyx Bridge, Pacific Hall, Streisinger Hall, University Health Services, Volcanology, Willamette Hall, and ZIRC

Scope:  Due to a leaking steam condensate valve and a damaged temperature probe wire, the autoclave clean steam heat exchanger will be shut down. Chemical treated steam will be cross connected to the pipeline for the duration of the shutdown.

Services Impacted

·           Clean steam will be unavailable but chemically treated 60 psi steam will be cross connected and routed through the pipeline for the duration of the shutdown.

·           No building heat or hot water will be impacted.

Extra Notes:  We will send out a notice when the system is back online.

Work Performed By:  CPFM Utilities & Energy

ContactKyle Wilson, CPFM Utilities Maintenance Manager, 541-346-2246