PLC Air Handling Systems Shutdown 11/20/20

Building Impacted:  Prince Lucien Campbell (PLC)

Scope:  Facilities Services is currently responding to the impacts of the recent fire/smoke event.  As a result, all building air handling systems will be taken off-line, cleaned and all filters replaced.

Begin:  Friday, November 20th, 2020 at 8:00 am

End:      Friday, November 20th, 2020 at 3:00 pm

Services Impacted:  This will affect the building’s cooling, cooling tower, heating, and HVAC air supply.

Extra Notes:  Attached is the link to the original campus wide emergency HVAC filter replacement project notice  https://blogs.uoregon.edu/cpfmnotifications/2020/09/21/campus-wide-hvac-filter-replacement/

Work Performed By:   UO CPFM Facilities Services

ContactKen Straw, CPFM Mechanical and Plumbing Shop Manager, 541-346-5406

Gerlinger Annex Air Handling Systems Shutdown 11/18/20

Building Impacted:  Gerlinger Annex

Scope:  Facilities Services is currently responding to the impacts of the recent fire/smoke event.  As a result, all building air handling systems will be taken off-line, cleaned and all filters replaced.

Begin:  Wednesday, November 18th, 2020 at 8:00 am

End:      Wednesday, November 18th, 2020 at 3:00 pm

Services Impacted:  This will affect the building’s cooling, cooling tower, heating, and HVAC air supply.

Extra Notes:  Attached is the link to the original campus wide emergency HVAC filter replacement project notice  https://blogs.uoregon.edu/cpfmnotifications/2020/09/21/campus-wide-hvac-filter-replacement/

Work Performed By:   UO CPFM Facilities Services

ContactKen Straw, CPFM Mechanical and Plumbing Shop Manager, 541-346-5406

Gerlinger Hall Air Handling Systems Shutdown 11/16/20

Building Impacted:  Gerlinger Hall

Scope:  Facilities Services is currently responding to the impacts of the recent fire/smoke event.  As a result, all building air handling systems will be taken off-line, cleaned and all filters replaced.

Begin:  Monday, November 16th, 2020 at 8:00 am

End:      Monday, November 16th, 2020 at 3:00 pm

Services Impacted:  This will affect the building’s cooling, cooling tower, heating, and HVAC air supply.

Extra Notes:  Attached is the link to the original campus wide emergency HVAC filter replacement project notice  https://blogs.uoregon.edu/cpfmnotifications/2020/09/21/campus-wide-hvac-filter-replacement/

Work Performed By:   UO CPFM Facilities Services

ContactKen Straw, CPFM Mechanical and Plumbing Shop Manager, 541-346-5406

McArthur Court Air Handling Systems Shutdown 11/13/20

Building Impacted:  McArthur Court

Scope:  Facilities Services is currently responding to the impacts of the recent fire/smoke event.  As a result, all building air handling systems will be taken off-line, cleaned and all filters replaced.

Begin:  Friday, November 13th, 2020 at 8:00 am

End:      Friday, November 13th, 2020 at 3:00 pm

Services Impacted:  This will affect the building’s cooling, cooling tower, heating, and HVAC air supply.

Extra Notes:  Attached is the link to the original campus wide emergency HVAC filter replacement project notice  https://blogs.uoregon.edu/cpfmnotifications/2020/09/21/campus-wide-hvac-filter-replacement/

Work Performed By:   UO CPFM Facilities Services

ContactKen Straw, CPFM Mechanical and Plumbing Shop Manager, 541-346-5406

Jordan Schnitzer Museum of Art Air Handling Systems Shutdown 11/9/20 and 11/11/20

Building Impacted:  Jordan Schnitzer Museum of Art

Scope:  Facilities Services is currently responding to the impacts of the recent fire/smoke event.  As a result, all building air handling systems will be taken off-line, cleaned and all filters replaced.

Dates and Times:

  • Monday, November 9th, 2020 at 8:00 am – 3:00 pm
  • Wednesday, November 11th, 2020 at 8:00 am – 3:00 pm

Services Impacted:  This will affect the building’s cooling, cooling tower, heating, and HVAC air supply.

Extra Notes:  Attached is the link to the original campus wide emergency HVAC filter replacement project notice  https://blogs.uoregon.edu/cpfmnotifications/2020/09/21/campus-wide-hvac-filter-replacement/

Work Performed By:   UO CPFM Facilities Services

ContactKen Straw, CPFM Mechanical and Plumbing Shop Manager, 541-346-5406