Baker Downtown Center Air Handling Systems Shutdown 11/6/20

Building Impacted:  Baker Downtown Center

Scope:  Facilities Services is currently responding to the impacts of the recent fire/smoke event.  As a result, all building air handling systems will be taken off-line, cleaned and all filters replaced.

Begin:  Friday, November 6th, 2020 at 8:00 am

End:      Friday, November 6th, 2020 at 3:00 pm

Services Impacted:  This will affect the building’s cooling, cooling tower, heating, and HVAC air supply.

Extra Notes:  Attached is the link to the original campus wide emergency HVAC filter replacement project notice  https://blogs.uoregon.edu/cpfmnotifications/2020/09/21/campus-wide-hvac-filter-replacement/

Work Performed By:   UO CPFM Facilities Services

ContactKen Straw, CPFM Mechanical and Plumbing Shop Manager, 541-346-5406

 

1600 Millrace Air Handling Systems Shutdown 11/4/20

Building Impacted:  1600 Millrace

Scope:  Facilities Services is currently responding to the impacts of the recent fire/smoke event.  As a result, all building air handling systems will be taken off-line, cleaned and all filters replaced.

Begin:  Wednesday, November 4th, 2020 at 8:00 am

End:      Wednesday, November 4th, 2020 at 3:00 pm

Services Impacted:  This will affect the building’s cooling, cooling tower, heating, and HVAC air supply.

Extra Notes:  Attached is the link to the original campus wide emergency HVAC filter replacement project notice  https://blogs.uoregon.edu/cpfmnotifications/2020/09/21/campus-wide-hvac-filter-replacement/

Work Performed By:   UO CPFM Facilities Services

ContactKen Straw, CPFM Mechanical and Plumbing Shop Manager, 541-346-5406

1715 Franklin Air Handling Systems Shutdown 11/2/20

Building Impacted:  1715 Franklin

Scope:  Facilities Services is currently responding to the impacts of the recent fire/smoke event.  As a result, all building air handling systems will be taken off-line, cleaned and all filters replaced.

Begin:  Monday, November 2nd, 2020 at 8:00 am

End:      Monday, November 2nd, 2020 at 3:00 pm

Services Impacted:  This will affect the building’s cooling, cooling tower, heating, and HVAC air supply.

Extra Notes:  Attached is the link to the original campus wide emergency HVAC filter replacement project notice  https://blogs.uoregon.edu/cpfmnotifications/2020/09/21/campus-wide-hvac-filter-replacement/

Work Performed By:   UO CPFM Facilities Services

ContactKen Straw, CPFM Mechanical and Plumbing Shop Manager, 541-346-54063

West End of Millrace Drive Gravel Road Closure (West of Riverfront Parkway) Notice 10/23/20 and 10/26/20

Begin:  Friday, October 23rd, 2020 (daily)

End:      Monday, October 26th, 2020

Building(s) or Area(s) Impacted:  Gravel road next to the greenhouses between Gallery Walk and Riverfront Parkway

Scope:  The gravel road next to the greenhouses between Gallery Walk and Riverfront Parkway will be closed to all pedestrian, bike, and vehicle traffic on Friday, 10/23 and on Monday 10/26 for grading & paving work to tie-in the jug handle turnaround with the intersection of Riverfront Pkwy at the Garage project. The road will be open over the weekend (Saturday & Sunday).

Services Impacted:  Road closure Friday and Monday

Work Performed By:   Hoffman Construction

ContactJenna Shope, CPFM Owner’s Representative, 541-346-2281

Agate Hall 2nd Floor Restrooms Shutdown 10/22/20 – 1/31/21

UPDATE 10/26: This is an informational notice regard the second floor bathrooms in Agate Hall, rooms 201 & 223. Due to sealcoat failure on the floors, the bathrooms will be taken offline while the flooring is repaired or replaced. The lower layers of flooring contain asbestos, and there is concern that if the sealcoat continues to be impacted, the asbestos layers may start getting impacted as well. This decision is being made out of an abundance of caution, and the asbestos layer has not yet been impacted at this time. EHS and CPFM are currently working out repair or replacement options. We will provide additional information as we figure out our plan.

In the meantime, please use the first floor restrooms. Please feel free to contact me if you have questions.

Begin:  Thursday, October 22nd, 2020 – Effective immediately

End:      Unknown January 31, 2021

Building(s) or Area(s) Impacted:  Agate Hall Men’s Restrooms #201 & 223

Scope:  The Men’s second floor restrooms #201 & 223, have been closed for emergency repairs/construction.

Services Impacted:  Second floor Men’s restrooms shut down.

Special InstructionsPlease use Men’s restroom #125 on the south end of the building of the 1st floor, or the All-Gender restroom #125A, which is located next to it. Please use the first floor restrooms.

Work Performed By:   CPFM Facilities and a contractor

ContactAdam Jones, SRS Buildings Sciences Manager, 541-346-8397

Lillis Hall HVAC Shutdown 10/27/20 – 10/28/20

Begin:  Tuesday, October 27th, 2020 at 8:30 am

End:      Wednesday, October 28th, 2020 at 5:00 pm

Building(s) or Area(s) Impacted:  Lillis Hall

Scope:  The HVAC air supply AHU3 will be down for repairs.

Services Impacted:

  • 3rd and 4th floor east conditioned air supply will be off.
  • Will not affect restroom and north east offices on the same floors.

Work Performed By:   UO Campus Planning and Facilities Management BAS Department

Contact: Stacy Breaux, CPFM FS Bldg Automation Sys Field Supr, 541-521-5376 or Kevin Bloom, CPFM BAS Dept., 541-346-2319