Millrace Path Closure 8/24-8/31

Begin:  Monday, August 24th, 2020

End:      Monday, August 31st, 2020

Building(s) or Area(s) Impacted: Path along the north side of the Millrace between Gallery Walk and Riverfront Parkway

Scope: The path along the north side of the Millrace between Gallery Walk and Riverfront Parkway will be closed to all pedestrian and bike traffic beginning Monday 8/24 for 1 week. Grade work to tie-in the Knight Campus bridges over the Millrace will be taking place during this closure.

Extra Notes: Gallery Walk will remain open to the north of the pathway and the detour route will be the gravel road north of the Urban Farm.

Work Performed By: Hoffman Construction

Contact: Jenna Shope, CPFM Owner’s Representative, 541-346-2281