Klamath Hall Exhaust and Fume Hood Shutdown 7/7/20

Begin:  Tuesday, July 7th, 2020 at 5:00 am

End:      Tuesday, July 7th, 2020 at 7:30 am

Building(s) or Area(s) Impacted:  Klamath Hall – North Half of All Levels

Scope:  Workers need to enter the exhaust plenum to remove temporary measures. The lab exhaust needs shut off for their safety.

Services Impacted:  All exhaust and fume hood exhaust for the north half of all levels will be offline for the duration.

Special InstructionsPlease shut all fume hood sashes the evening before, on Monday July 6th.

Work Performed By:   Lease Crutcher Lewis

ContactDenise Stewart, CPFM Owner’s Representative, 541-346-2280 or 541-335-1258

LISB, Sidewalks, and Parking Lot 12B MRI Installation Advisory and Closures 7/6/2020

Begin:  Monday, July 6th, 2020 at 7:00 am

End:      Wednesday, July 8th, 2020 at 6:00 pm

Building(s) or Area(s) Impacted:  Lewis Integrative Science Building and Lot 12B

Scope:  The east end of Lot 12B, sidewalks, and the north entry to LISB will be closed July 6-8 to accommodate the delivery and installation of an MRI to the Lewis Center for Neuroimaging in LISB.

Services Impacted:

  • Sidewalks north of LISB and the north entry to LISB will be signed and closed.
  • All pedestrian traffic in this area will be rerouted south.

Work Performed By:   Ness Campbell, Siemens, and GBC

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880

CPFM Maintenance Yard Traffic Advisory 7/6/20 – 7/8/20

Begin:  Monday, July 6th, 2020 at 8:00 am

End:      Wednesday, July 8th, 2020 at 5:00 pm

Building(s) or Area(s) Impacted:  CPFM Maintenance Yard

Scope:  There will be a large volume of trucks bringing in gravel for the Back 40 expansion project. Over the course of three days, 200 trucks loads of gravel will be delivered. Users of the yard should exercise extra caution during this time.

Services Impacted:  Areas around buildings 130, 136, and the CPS Plant.

Work Performed By:  On Demand Excavation

ContactKevin Farthing, CPFM Assoc. Dir Facilities Services Env., 541-346-2857

Tykeson Hall Bulletin Board Installation Advisory 7/9/2020

Begin:  Thursday, July 9th, 2020 at 9:00 am

End:      Thursday, July 9th, 2020 at 3:00 pm

Building(s) or Area(s) Impacted:  Tykeson Hall

Scope:  A contractor will be installing bulletin boards in the advising offices.

Services Impacted:  Access around workers in the immediate areas of suites 101 and 250, along with related noise.

Work Performed By:   Hyphn

ContactMartina Oxoby, CPFM Owner’s Representative, 541-346-5880