Walton Hall SE Corner Parking Lot Removal 6/15/20

Begin:  Monday, June 15th, 2020

End:      Monday, June 15th, 2020

Building(s) or Area(s) Impacted:  Small parking lot at the SE corner of Walton Hall.

Scope:  We will be removing the small parking lot at the corner of 15th Ave and Agate. This temporary lot was permitted by the City until the university assumed control of the Hayward Field project. Due to the demolition contractor’s tight schedule over the summer, we need to remove the lot now.

Services Impacted:  This parking lot will no longer be available for use.

Special Instructions:  A sign will be posted warning users not to park there on Monday.

Work Performed By:  Wildish Construction

ContactWork Control Center, Campus Planning and Facilities Management, 346-2319