Begin: Monday, May 18th, 2020
End: Friday, May 22nd, 2020
Building or Area Impacted: 13th Ave Garage
Scope: The gate equipment is being replaced throughout the coming week. (See schedule below)
- Monday, May 18th – Begin removing equipment (starting with the exit lane)
- Tuesday, May 19th – Continue removing equipment and begin installation
- Wednesday, May 20th – Continue installation
- Thursday, May 21st – Test equipment and work out bugs
- Friday, May 22nd – Wrap up project
Services Impacted: The contractor will keep one lane open at all times, but drivers in the area should exercise caution.
Contact: James McGladrey, UO Transportation Services Field Operations Manager, 541-346-2676