Klamath Hall Heating Water Shutdown 5/19/20

Begin: Tuesday, May 19th, 2020 at 7:00 am

End: Tuesday, May 19th, 2020 at 3:30 pm

Building or Area Impacted: Klamath Hall 3rd floor

Scope: This shutdown is to change out the impellers in the heating water pumps to provide the additional pressure needed to feed the level 2 renovation.

Services Impacted: Temperatures may decrease for a portion of the shutdown duration on level 3.

Work Performed By: Lease Crutcher Lewis

Contact: Denise Stewart, CPFM Owner’s Representative, 541-346-2280 or 541-335-1258