Thompson University Center Mechanical Work Advisory 2/28/20 – 3/4/20

Begin:  Friday, February 28th, 2020 at 6:30 am

End:      Wednesday, March 4th, 2020 at 5:00 pm

Building and Areas Impacted:  Thompson University Center’s Break Room 308, Mechanical Room 309, 3rd Floor Hall, and South Stairwell

Scope:  Install mini split unit in room 308

Services Impacted: 

  • The south stairwell and room 308 may not be available for use during Friday, 2/28/2020, through Wednesday, 3/4/2020.
  • There will be noise on the roof, south stairwell, 3rd floor halls and room 308 throughout the project.

Proposed Schedule:

  • Friday, 2/28/2020, 6:30 am – a crane will be onsite to lift equipment to the south roof.
  • Monday and Tuesday, 3/2 to 3/3/2020, Alliant Systems will have an electrician and service technician onsite to install the indoor and outdoor units.
  • Wednesday, 3/4/2020, project is scheduled to be completed by end of day.

Extra Notes:  Work will be performed by Alliant Systems

ContactMelinda Seeley, CPFM Real Estate Prop Specialist, 541-346-5550

Straub Hall Exterior Window Washing 2/29/2020 – 3/3/2020

Begin:  Saturday, February 29th, 2020 at 8:00 am

End:      Tuesday, March 3rd, 2020 at 5:00 pm

Building Impacted: Straub Hall

Scope: The exterior windows will be washed.

Services Impacted: Due to the use of the lift, sidewalks and walkways may be partially blocked, but will not interfere with ADA entrances.

Extra Notes: Work will be performed by DDJ.

Special Instructions: Please close all exterior windows on these dates.

Contact: Kevin Farthing at 541-359-6633 or kfarthin@uoregon.edu