Onyx 292 HVAC and Refrigerant Equipment Installation: 9/10-10/9

Update 10/4: This project has been extended due to humidity issues and is expected to be completed by Wednesday October 9th.

 

Update 9/26: This project has been extended and is expected to be completed by Friday October 4th.

 

Starting on Tuesday, September 10th and running through Friday, September 27th October 4th, contractors will be installing new HVAC and refrigerant equipment in Onyx 292. This work will entail demolition and removal of existing equipment through the exterior of the building. There will be boom lifts and safety equipment operating the the courtyard outside Onyx Bridge and Cascade Hall. Safety barricades will be in place to redirect pedestrian and bicycle traffic. If you have any questions or concerns, please contact Associate Director of Facilities, Jim Cody at 541-346-2302.