Frohnmayer Music Building Roof Project 8/12-11/27/19

Update 11/18: This project is now complete.

Update 10/29: This project has been extended and is expected to be completed by November 27th.

Update 9/30: This project has been extended and is expected to be completed by October 31st.

 

From August 12 – September 30 October 31 November 27th, the southern portion of the Frohnmayer Music Building will be reroofed.

Building users can expect to hear normal and occasional construction noises, such as hammering and drilling. Occupants might also see the contractor or UO personnel enter/exit the building with tools and materials during normal business hours and as early as 6:30 a.m. We anticipate no further utility disruptions or shutoffs during this time, but should unexpected incidents occur, additional notices will be distributed.

This work involves demo, abatement, prep work, laying new roofing material, and installing safety features. The operation also will include a crane at the work site.

Anderson Roofing will perform the work; Rose City will handle any abatement issues.

Please direct any questions or concerns to Project Manager Theo Davis at 541-346-1012 or tdavis1@uoregon.edu.

Huestis Fire Sprinkler Work 8/12/19

On Monday, August 12, from 7 a.m.–3 p.m., work will be performed on the fire sprinkler system, with no impact to building occupants.

LCL will perform the work.

Horns, Strobes, and Speakers on the fire alarm system will not sound after the scheduled time. Provisions have been taken to monitor the building fire systems during this time. Any alarms that occur after the scheduled time should be considered real events, and occupants should evacuate as usual, per the U of O Emergency Procedures.

For questions regarding these emergency evacuation procedures, visit the Emergency Management & Continuity website at https://safety.uoregon.edu/evacuations.

Please direct questions or concerns to Colin Brennan at brennan@uoregon.edu or 541-346-8242.