Rooftop Work Advisory Computing Center, PLC, Miller Theater, and JSMA 8/27 – 8/30

Building Occupants,

August 27 – 30, 2018 a contractor will be working on the below-listed roofs working on rooftop equipment that will improve campus communications reception in Computing Center, PLC, Miller Theater, and JSMA.  You may hear noise or see contractors working in the following locations:

Computing Center Monday 8/27
6:00 am – 7:30 am rooftop work and drilling

PLC Monday 8/27/18 

8:00 am – 10:00 am rooftop work

Miller Theater Monday 8/27

1:00 pm – 3:00 pm rooftop work

PLC Tuesday 8/28

7:00 am – 9:00 am rooftop work

JSMA Tuesday 8/28

7:00 am – 9:00 am rooftop conduit work and repairs

Computing Center, PLC, Miller Theater and JSMA Wednesday and Thursday 8/29 & 8/30 

All day rooftop conduit work and repairs

Please contact CPFM Project Manager Jana Gerow 541-346-8317 office 970-640-0176 cell with any questions or concerns.