3/5 – 3/6: Tykeson Hall Crane Logistics Plan

Campus Community,

As part of the Tykeson project, the below logistics map shows the scope of work for the tower crane which will be constructed next Monday, March 5, 2018, and Tuesday, March 6, 2018. This work requires a truck to be parked in the west end of Johnson lane, north of the access lane to JSMA and Parking Lot #25. A truck will be in place the morning of March 5, starting at 8:00 am and in place all day March 6. Access to the JSMA lot will remain open with a flagger to direct traffic.

For questions or concerns please contact CPFM Design and Construction Project Manager Martina Oxoby at 541-346-5880.